Granted
Rue des Sablons
Bruxelles · 04/PFU/161077 · Permis d'urbanisme unique délivré par le FD
Rue des Sablons, Bruxelles: energy works. Case octroyé, lodged on 26 January 2005. The decision was notified on 5 August 2005, 191 days after lodging.
Renouveler les installations électriques de la chapelle Saint-Marcou à l'église Notre-Dame du Sablon| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 26 January 2005 | date the file was received |
| Consultation committee | 12 July 2005 | |
| Decision notified | 5 August 2005 | 191 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)