Granted
Rue de Verdun
Bruxelles · 04/PFU/171063 · Permis d'urbanisme unique délivré par le FD
Rue de Verdun, Bruxelles: other. Case octroyé, lodged on 21 November 2005. The decision was notified on 8 February 2006, 79 days after lodging.
onderhaudswerken aan 3 hoogspanningsmasten (P33, 34 en 35)| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 21 November 2005 | date the file was received |
| Decision notified | 8 February 2006 | 79 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)