Granted
Bois de la Cambre
Bruxelles · 04/PFU/1731634 · Permis d'urbanisme unique délivré par le FD
Bois de la Cambre, Bruxelles: other. Case octroyé, lodged on 14 November 2019. The decision was notified on 24 December 2019, 40 days after lodging.
placer d'installations temporaires| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 November 2019 | date the file was received |
| Decision notified | 24 December 2019 | 40 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 18 m | Tree felling | Abattre 211 arbres, dont 178 morts et 33 moribonds. | 2024 |
| 61 m | Extension or raising | Construire une annexe attenante au pavillon existant. L'annexe contiendra un WC PMR et deux WC, ainsi qu'un local destin | 2024 |
| 62 m | New construction | Placer des toilettes mobiles dans le bois de la cambre | 2022 |
| 119 m | Public space | Placer des infrastructures dans le Bois de la Cambre pour le déroulement du festival "Théâtres Nomades" du 09 au 23 août | 2024 |
| 125 m | Public space | Installer temporairement différentes infrastructures mobiles (chapiteaux, tentes, etc.) au Bois de la Cambre, au niveau | 2025 |
Other nearby cases : 04/PFU/1829404, 04/PFU/1822767, 04/PFU/1987646, 04/PFU/1892050, 04/PFU/1801430, 04/PFU/1864561, 04/PFU/1952346, 04/PFU/2018320
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)