Rue aux Laines 30, Bruxelles: heavy renovation. Case octroyé, lodged on 15 March 2006. The decision was notified on 22 October 2007, 586 days after lodging. The project creates 54 m² of housing.
rénover un immeuble unifamilial| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 March 2006 | date the file was received |
| Consultation committee | 6 March 2007 | |
| Decision notified | 22 October 2007 | 586 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 21 m | Heavy renovation | Régularisation du permis 04/PFU/646883 concernant les modifications de l'escalier du duplex 3 et de la fenêtre du premie | 2022 |
| 30 m | — | g | 2023 |
| 30 m | Tree felling | Mettre en conformité les aménagements (extérieurs) déjà réalisés. | 2023 |
| 44 m | Heavy renovation | Régulariser les travaux d'urgences lié à la mérule (décapage d’enduits, remplacements de linteaux métalliques, restaurat | 2024 |
| 44 m | Roof | Régulariser diverses modifications des travaux en toiture effectués pendant le chantier consécutif au permis 04/PFU/1738 | 2024 |
Other nearby cases : 04/PFU/2025746, 04/PFU/2033070, 04/PFU/1911341, 04/GOU_PU/1945093, 04/PU/1908490, 04/PFU/1844033, 04/PFU/1908716, 04/PFU/1924598, 04/PFU/1953622, 04/PFU/1862806, 04/PFU/2008999, 04/PU/1906359, 04/PFU/1910498, 04/PU/1854242, 04/PFU/1856470, 04/PU/1903566, 04/PU/1902719, 04/PU/1908251, 04/PU/1942462, 04/PU/1971804, 04/PFU/1942313, 04/PFU/1971590, 04/PU/2008041, 04/PFU/1995000, 04/PFU/1862850
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)