Parc Leopold

Bruxelles · 04/PFU/179600 · Permis d'urbanisme unique délivré par le FD

Parc Leopold, Bruxelles: public space. Case octroyé, lodged on 22 December 2006. The decision was notified on 31 May 2007, 160 days after lodging.

poser une nouvelle liaison souterraine dans le parc Liaison souterraine 150KV Dhanis - Wiertz
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on22 December 2006date the file was received
Consultation committee3 April 2007
Decision notified31 May 2007160 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Consultation committee
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)