Carrefour de l'Europe 1
Bruxelles · 04/PFU/1826480 · Permis d'urbanisme unique délivré par le FD
Carrefour de l'Europe 1, Bruxelles: heavy renovation. Case octroyé, lodged on 16 December 2021. The decision was notified on 5 January 2023, 385 days after lodging.
Plaatsen van 3 bijkomende liften| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 16 December 2021 | date the file was received |
| Decision notified | 5 January 2023 | 385 days |
| Works started | 20 February 2025 | |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Other | remplacer les distributeurs de billets | 2021 |
| 0 m | Façade and windows | Réaliser une ouverture dans le mur extérieur et le sol pour y installer une nouvelle bouche d’aération. | 2022 |
| 0 m | Change of use | rénovation de guichet national et guichet international en back office | 2021 |
| 0 m | Other | Ombouwen van de huidige cash-automaten in het station Brussel Centraal. | 2022 |
| 0 m | Public space | Préserver le carrelage existant dans le hall d’entrée de la Gare de Bru. Central et limiter les risques de dégradation, | 2026 |
Other nearby cases : 04/PFU/1939786, 04/PFU/2003232, 04/PU/1963468, 04/PFU/1947994, 04/PFD/1906362, 04/PFD/1845467, 04/PFU/2016519, 04/PU/1844887, 04/PU/1837252, 04/PU/1979574, 04/PU/2016609, 04/SFD/1922122, 04/PU/1975541, 04/PU/1842790, 04/PFD/1969054, 04/PFU/1855692, 04/GOU_PU/1988658, 04/PFU/1922275, 04/PFU/2039459, 04/PFU/1982042, 04/PFU/1870725, 04/PU/1949203, 04/PU/1950641, 04/PFD/2007952, 04/PU/1986050
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)