Skip to content
AltUrb
Granted

Place De Brouckère 23–39

Bruxelles · 04/PFU/1871172 · Permis d'urbanisme unique délivré par le FD

Place De Brouckère 23–39, Bruxelles: other. Case octroyé, lodged on 3 February 2023. The decision was notified on 4 April 2023, 60 days after lodging.

Réaliser des études et des sondages préalables
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on3 February 2023date the file was received
Decision notified4 April 202360 days
Works started31 July 2023
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
6 mFaçade and windowsREMPLACER DES FENÊTRES À GUILLOTINE ET RESTITUTION DES DOUBLES PORTES DE LA FUTURE RÉCEPTION2026
17 mHeavy renovationRénover les parties non classées de l’hôtel Métropole, installer un espace spa avec piscine au sous-sol et modifier et a2023
18 mHeavy renovationRestaurer les parties classées de l'Hotel Métropole.2023
34 mSigns and advertisingplacer une enseigne parallèle et une enseigne perpendiculaire à la façade2022
35 mSigns and advertisingplacer 7 enseignes parallèles2025

Other nearby cases : 04/PU/1966198, 04/PFU/2002217, 04/PFU/1835969, 04/PU/1836200, 04/PU/1900007, 04/PU/1975507, 04/PFD/1967679, 04/PU/1894332, 04/PU/1905296, 04/PU/1943143, 04/PU/1905973, 04/PFU/1942811, 04/PFU/1994196, 04/PU/1837105, 04/PU/1850903, 04/PFU/1848711, 04/PU/1929991, 04/PFU/1976145, 04/PU/2030888, 04/PU/2013356, 04/PFD/1821766, 04/PFU/1906351, 04/PU/1933559, 04/PU/1859218, 04/PFU/1947677

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)