Granted
Parc de Bruxelles
Bruxelles · 04/PFU/187722 · Permis d'urbanisme unique délivré par le FD
Parc de Bruxelles, Bruxelles: tree felling. Case octroyé, lodged on 17 January 2008. The decision was notified on 15 February 2008, 29 days after lodging.
abattre 25 arbres dans divers sites protégés de la Ville| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 17 January 2008 | date the file was received |
| Decision notified | 15 February 2008 | 29 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)