Rue des Sablons 1, Bruxelles: roof. Case octroyé, lodged on 24 July 2023. The decision was notified on 30 October 2023, 98 days after lodging.

Restaurer la charpente et de la toiture au droit du transept Sud
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on24 July 2023date the file was received
Decision notified30 October 202398 days
Works started22 September 2025
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
46 mPublic spaceMise en conformité : Mettre en place pérenne d’une œuvre d’art destinée à l’espace public, sur un site identifié.2026
59 mSigns and advertisingplacer 4 enseignes en façade avant2024
59 mSigns and advertisingPlacement de 5 enseignes 2023
59 mSplit into dwellingsdiviser un commerce en 3 unités commerciales distinctes et modifier les portes d'entrées2023
59 mSigns and advertisingPlacement de 5 enseignes 2024

Other nearby cases : 04/PFU/1910839, 04/PFU/1960982, 04/PFD/1837409, 04/PU/1988768, 04/PU/1822086, 04/PFD/2034039, 04/PU/2019472, 04/PU/1951145, 04/PU/1843621, 04/PU/2032678, 04/PFU/1944537, 04/PU/1942052, 04/GOU_PU/1870232, 04/PU/2028699, 04/PFD/2024009, 04/PU/1853476, 04/SFD/1840242, 04/PU/1906359, 04/PU/1917819, 04/PU/1906096, 04/PFU/1958822, 04/PU/1959199, 04/PU/2026353, 04/PU/1842095, 04/PU/2031280

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)