Bois de la Cambre, Bruxelles: other. Case octroyé, lodged on 5 May 2010. The decision was notified on 28 May 2010, 23 days after lodging.

installer une halte de ravitaillement dans le cadre de la Fête de l'Environnement du dimanche 6 juin 2010. En collaboration avec le Beau Vélo de Ravel
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on5 May 2010date the file was received
Decision notified28 May 201023 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.