Altaica Urban
Granted

Bois de la Cambre

Bruxelles · 04/PFU/384063 · Permis d'urbanisme unique délivré par le FD

Bois de la Cambre, Bruxelles: other. Case octroyé, lodged on 4 January 2011. The decision was notified on 2 March 2011, 57 days after lodging.

Réaliser des travaux de sondages et de carottages dans le site classé
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on4 January 2011date the file was received
Decision notified2 March 201157 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.