Boulevard Adolphe Max 28–36, Bruxelles: heavy renovation. Case octroyé, lodged on 24 January 2013. The decision was notified on 27 September 2013, 246 days after lodging. The project creates 28 m² of housing.
Transformer l'intérieur d'un immeuble à usage mixte: créer un escalier intérieur, 2 petits plateaux et ouvrir une baie (régularisation)28m²
Housing floor area created
| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 24 January 2013 | date the file was received |
| Decision notified | 27 September 2013 | 246 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.