Parc de Bruxelles

Bruxelles · 04/PFU/494064 · Permis d'urbanisme unique délivré par le FD

Parc de Bruxelles, Bruxelles: new construction. Case octroyé, lodged on 8 November 2013. The decision was notified on 7 January 2014, 60 days after lodging.

Installer le chantier pour la construction d'une salle de répétition pour le théâtre Royal du Parc
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on8 November 2013date the file was received
Decision notified7 January 201460 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.