Granted
Square Clémentine
Bruxelles · 04/PFU/701024 · Permis d'urbanisme unique délivré par le FD
Square Clémentine, Bruxelles: tree felling. Case octroyé, lodged on 4 October 2018. The decision was notified on 13 December 2018, 70 days after lodging.
Vellen van 1 gevaarlijke boom op het Clementinasquare.| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 October 2018 | date the file was received |
| Decision notified | 13 December 2018 | 70 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)