Granted

Bois de la Cambre

Bruxelles · 04/PFU/702675 · Permis d'urbanisme unique délivré par le FD

Bois de la Cambre, Bruxelles: other. Case octroyé, lodged on 22 October 2018. The decision was notified on 10 January 2019, 80 days after lodging.

Placement d'installations temporaires à caractère événement non ancrées dans le sol
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on22 October 2018date the file was received
Decision notified10 January 201980 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.