Bruxelles · 04/PU/1697066 · Permis d'urbanisme privé
Rue de Ransbeek 310, Bruxelles: roof. Case octroyé, lodged on 14 December 2018. The decision was notified on 9 May 2019, 146 days after lodging.
créer une baie, ajouter une coupole, placer des pompes à chaleur supplémentaires dans le bâtiment H| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 December 2018 | date the file was received |
| Decision notified | 9 May 2019 | 146 days |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 4 m | Extension or raising | d'une part, rehausser le bâtiment H du complexe Solvay et, d'autre part, poser un container de refroidissement d'eau (wa | 2022 |
| 4 m | New construction | Construire un container pour un groupe de secours & installer une citerne à mazout | 2024 |
| 104 m | Demolition | démolir un ensemble de locaux préfabriqués devant le bâtiment E du campus Solvay, modifier un châssis et placer une port | 2023 |
| 124 m | Heavy renovation | créer un atrium avec démolition partielle d'une dalle et de la façade arrière entre les deux ailes du bâtiment, modifier | 2021 |
| 124 m | Demolition and reconstruction | démolir 5 hangars (mise en conformité) et reconstruire des cabines haute et basse tensions et un transformateur statique | 2022 |
Other nearby cases : 04/PU/1866264, 04/SFD/1930620, 04/PU/1968648, 04/PU/1939791, 04/PU/1975715, 04/PU/1908040