Bruxelles · 04/PU/1795362 · Permis d'urbanisme privé

Mariënborre 40A, Bruxelles: new construction. Case octroyé, lodged on 5 August 2021. The decision was notified on 30 June 2022, 329 days after lodging.

construire une cabane en torchis (local de pause des travailleurs) et un atelier (mise en conformité);
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on5 August 2021date the file was received
Public inquiry14 April 2022 – 29 April 2022
Consultation committee7 June 2022
Decision notified30 June 2022329 days
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
163 mNew constructionconstruire une cabine haute tension2024
163 mNew constructionConstruire une cabine haute tension.2025
173 mDemolitionDémolir 4 bâtiments existants répartis le long de la rue Mariënsteen et réaménager les terrains, tel que suit : - démoli2022

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)