Harenberg 96
Bruxelles · 04/PU/1950018 · Permis d'urbanisme privé
Harenberg 96, Bruxelles: new construction. Case octroyé, lodged on 4 July 2024. The decision was notified on 25 June 2026, 721 days after lodging. The project creates 272 m² of housing.
construire une maison unifamiliale| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 July 2024 | date the file was received |
| Public inquiry | 11 December 2025 – 26 December 2025 | |
| Consultation committee | 20 January 2026 | |
| Decision notified | 25 June 2026 | 721 days |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | New construction | construire un immeuble avec deux duplex | 2023 |
| 59 m | New construction | construire un immeuble d'habitation (R+2) composé de 3 logements (lot 1) | 2022 |
| 105 m | New construction | Implanter une cabine à haute tension avec une clôture de sécurité intégrant des haies | 2026 |
| 105 m | New construction | Implantation d'une cabine à haute tension | 2026 |
| 111 m | Demolition and reconstruction | démolir une annexe et une véranda pour construire une nouvelle annexe avec lanterneau | 2023 |
Other nearby cases : 04/PU/1862076, 04/PU/1835122, 04/PU/1860595, 04/PU/1846971, 04/PFD/1836201, 04/PFD/1895129, 04/PFD/1849442, 04/PFD/1993577, 04/PU/1895277, 04/PU/1810861, 04/PU/1940919, 04/PU/1950038, 04/PFD/2015869, 04/PFD/1841728, 04/PU/1979376, 04/PU/1936058, 04/PU/1955673, 04/PU/1956771, 04/PU/1931425, 04/PU/1856720, 04/PU/2029339, 04/PU/1862066, 04/PU/1946377, 04/PU/1847225
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)