Granted

Avenue de Vilvorde 164

Bruxelles · 04/PU/1951057 · Permis d'urbanisme privé

Avenue de Vilvorde 164, Bruxelles: new construction. Case octroyé, lodged on 12 July 2024. The decision was notified on 26 May 2025, 318 days after lodging.

bouwen van een technische installatie (batterijen)
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on12 July 2024date the file was received
Public inquiry30 January 2025 – 14 February 2025
Consultation committee25 February 2025
Decision notified26 May 2025318 days
Works started23 June 2025
Floor areasnot reported by the source
Competent authorityBruxelles

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted
  8. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
110 mNew constructionCréation d'un équipement d'intérêt public "centre de broyage temporaire couvert", sur le site "Schaerbeek-Formation"2026
144 mNew constructionConstruire une plate-forme trimodale et un bâtiment d'accueil avec aménagement paysager associé. Mettre en conformité l'2024
223 mSigns and advertisingrégulariser le placement d’un dispositif publicitaire présentant un panneau d'une superficie de +- 36 m²2022
223 mSigns and advertisingMaintenir un dispositif publicitaire d'une superficie de 36 m² au n°130 avenue de Vilvorde 2023
237 mSigns and advertisingrenouveler le PU A444/2016 pour le maintien d'un dispositif publicitaire monopied non éclairé, sur terrain non-bâti2022

Other nearby cases : 04/PFD/1811459, 04/PU/1898890

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)