Granted
Avenue du Brésil 1
Bruxelles · 04/PU/2001944 · Permis d'urbanisme privé
Avenue du Brésil 1, Bruxelles: heavy renovation. Case octroyé, lodged on 18 September 2025. The decision was notified on 22 December 2025, 95 days after lodging.
transformer une villa 4 façades (mise en conformité)| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 September 2025 | date the file was received |
| Decision notified | 22 December 2025 | 95 days |
| Works started | 6 January 2026 | |
| Floor areas | — | not reported by the source |
| Competent authority | Bruxelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 28 m | Façade and windows | remplacer partiellement des châssis | 2024 |
| 61 m | Public space | Réaliser une tranchée en site classé du Bois de la Cambre. | 2023 |
| 76 m | Tree felling | abattre un arbre | 2025 |
| 82 m | Heavy renovation | apporter des modifications d'aménagements dans l'appartement du rez-de-chaussée, aile gauche, impliquant la création d'u | 2023 |
| 91 m | Tree felling | abattre un cèdre gravement endommagé de la résidence d'ambassadeur allemande auprès de l'OTAN. | 2022 |
Other nearby cases : 04/PU/1833253, 04/PU/1967830, 04/PFD/1969788, 04/PU/1912353, 04/PU/2038741, 04/PU/1863120, 04/PU/1958767, 04/PU/1982928, 04/PU/1898263, 04/PU/1870053
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)