Altaica Urban
Granted

Avenue de Broqueville 94

Woluwe-Saint-Lambert · 05/IPE/1972994 · Permis d'environnement

Avenue de Broqueville 94, Woluwe-Saint-Lambert: —. Case octroyé, lodged on 4 February 2025. The decision was notified on 2 April 2025, 57 days after lodging.

BX3208
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on4 February 2025date the file was received
Decision notified2 April 202557 days
Works started2 April 2025
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mMerger of dwellingsrégulariser la transformation de deux appartements en une unité de logement au septième étage de l'immeuble2026
32 mExtension or raisingrégulariser les travaux effectués (modification de la toiture, fermeture d'une terrasse, remplacement de châssis, ...) e2024
66 mPublic spaceRemplacer un mobilier urbain d'information à proximité des entrées du métro Josephine-Charlotte par un mobilier plus est2023
85 mTree fellingabattre un arbre dans le jardin de l'immeuble2024
94 mExtension or raisingconstruire un étage supplémentaire ainsi qu'un petit volume donnant accès à la nouvelle toiture végétalisée et régularis2024

Other nearby cases : 18/SFD/2007535, 18/PU/1959156, 18/PU/1960579, 18/PU/1990780, 18/PU/2019236, 18/PU/2021695, 18/PU/1965995, 18/PFD/2038803, 18/SFD/1995506, 18/PU/1963196, 18/PU/2034364, 18/PU/1857489, 18/PU/2010941, 18/PU/2008836, 18/PU/1994285, 18/PU/1932120, 18/PU/1867761, 18/PU/1860686, 18/PU/1951071, 18/PU/1912561, 18/PU/2008236, 18/SFD/1825307, 18/PU/2022807, 18/PU/1972374, 18/SFD/2000232

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)