Skip to content
AltUrb
Granted

Rue Demot 28–30

Etterbeek · 05/IPEPLP/482219 · Prolongation de PE

Rue Demot 28–30, Etterbeek: operation of installations. Case octroyé, lodged on 24 January 2013. The decision was notified on 13 February 2014, 385 days after lodging.

prolongation pour l'exploitation d'un immeuble de bureaux
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on24 January 2013date the file was received
Decision notified13 February 2014385 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
56 mChange of userégulariser les modifications apportées au duplex sous-sol et rez d'un immeuble à appartements pour passer de 1 à 3 cham2021
65 mChange of usechanger l'affectation d'un bureau en équipement (cabinet dentaire)2026
68 mExtension or raisingrehausser, agrandir et transformer un immeuble d'équipement scolaire pour y aménager quatre logements2024
72 mSplit into dwellingsrégulariser les modifications apportées à un immeuble de logements : aménagement d’un logement supplémentaire au sous-so2024
75 mHeavy renovationrénover un immeuble de 3 logements ainsi qu'abattre un arbre à haute tige2023

Other nearby cases : 05/PU/1854799, 05/PU/1995547, 05/PU/1965000, 05/PU/2021499, 05/PU/1943775, 05/PU/1950660, 05/PU/1799126, 05/PFD/2027317, 05/PU/2026934, 05/PU/1811478, 05/PU/1912349, 05/PU/1896246, 05/PFD/2008004, 05/PU/1966173, 05/PU/1823736, 05/PU/2042031, 05/PU/1983758, 05/PU/1998292, 05/PU/1968024, 05/PU/2028857, 05/PU/1922615, 05/PU/2041843, 05/PU/2027570, 05/PU/1925902, 05/PU/1912274

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)