Avenue d'Auderghem 124–130
Etterbeek · 05/IPETMP/603823 · Permis d'environnement temporaire
Avenue d'Auderghem 124–130, Etterbeek: operation of installations. Case annulé, lodged on 24 June 2016. The decision was notified on 13 July 2016, 19 days after lodging.
asbestwerf| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 24 June 2016 | date the file was received |
| Decision notified | 13 July 2016 | 19 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 15 m | Roof | régulariser l'aménagement d'un logement au 4e étage (combles) d'un immeuble et le réaménager en duplex 2 chambres (espac | 2025 |
| 15 m | Split into dwellings | régulariser l'aménagement d'un 5e logement (2 chambres) dans les combles d'un immeuble, la modification des châssis au 4 | 2025 |
| 32 m | Energy works | installer une pompe à chaleur dans le jardin, le long de la façade arrière | 2024 |
| 41 m | Roof | modifier le revêtement de la toiture à versants ainsi que l'isoler par l'extérieur (sarking) | 2023 |
| 52 m | Change of use | changer l'affectation du rez-de-chaussée de bureau en commerce au sein d'un immeuble comportant 3 logements aux étages | 2025 |
Other nearby cases : 05/PU/1967563, 05/PU/2040819, 05/PU/1922615, 05/PU/2027570, 05/PU/2040598, 05/PU/1913863, 05/PU/1935543, 05/PU/1983758, 05/PU/1859438, 05/PU/1836918, 05/PU/2002757, 05/PU/2002132, 05/PU/1952180, 05/PU/1995042, 05/PU/1983852, 05/PU/2010415, 05/PU/1833747, 05/PU/1857533, 05/PU/1811262, 05/PU/1825782, 05/PU/1904269, 05/PU/1992723, 05/PU/1966173, 05/PU/1947273, 05/PU/1912274
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)