Rue Général Leman 152
Etterbeek · 05/PU/1876921 · Permis d'urbanisme privé
Rue Général Leman 152, Etterbeek: new construction. Case octroyé, lodged on 31 December 1885. The decision was notified on 27 June 1886, 178 days after lodging. It comprises 1 dwellings.
CONSTRUIRE une maison de 6 m de façade DAILLIET A, d| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 31 December 1885 | date the file was received |
| Decision notified | 27 June 1886 | 178 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 11 m | Façade and windows | modifier la vitrine d'un rez commercial | 2026 |
| 13 m | Retail or horeca fit-out | changer l'utilisation d'un commerce avec consommation sur place afin d'y réaliser des grillades et fritures | 2025 |
| 25 m | Extension or raising | régulariser, en application de l'article 330§3 du CoBAT, les modifications apportées à une maison unifamiliale dont la c | 2024 |
| 25 m | Façade and windows | modifier la façade avant par la restauration du balcon, le remplacement du garde-corps (lisses horizontales et dés en bé | 2026 |
| 39 m | Split into dwellings | diviser une maison unifamiliale avec commerce en un bureau au rez avant et deux logements, démolir une partie de l'annex | 2024 |
Other nearby cases : 05/PU/1833747, 05/PU/2010415, 05/PU/1811262, 05/PU/1859438, 05/PU/1904269, 05/PU/1941899, 05/PU/1935543, 05/PU/1913863, 05/PU/1995042, 05/PU/1970223, 05/PU/1999978, 05/PU/1857533, 05/SFD/1825423, 05/PU/1827262, 05/PU/1992723, 05/PU/1903821, 05/PU/1934506, 05/PU/2035209, 05/PU/2005885, 05/PU/1947273, 05/PU/1914142, 05/PU/1968382, 05/PU/1829504, 05/PU/1828023, 05/PU/1867225
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)