Skip to content
AltUrb
Granted

Rue Philippe Baucq 139

Etterbeek · 05/PU/1877175 · Permis d'urbanisme privé

Rue Philippe Baucq 139, Etterbeek: new construction. Case octroyé, lodged on 1 January 1949. The decision was notified on 17 March 1949, 75 days after lodging.

CONSTRUIRE Une maison avec atelier 7 m faç 946 m3 HUTSEBAUT Georges, d
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 January 1949date the file was received
Decision notified17 March 194975 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
14 mTree fellingabattre un arbre à haute tige (hors voirie)2025
31 mTree fellingabattre 4 arbres en intérieur d'îlot2024
31 mTree fellingabattre un arbre (cytise) en zone de cours et jardins2025
33 m.2026
37 mHeavy renovationrégulariser les travaux non conformes au permis 7027 (2006) en ce qui concerne l'organisation de l'appartement deux cham2025

Other nearby cases : 05/PU/2023104, 05/PU/1941137, 05/PU/1951940, 05/PU/2044727, 05/PU/1989050, 05/PU/1833201, 05/PFD/1849484, 05/PU/1893683, 05/PU/1897277, 05/PU/1911242, 05/PU/1824844, 05/PU/2007479, 05/PU/1946398, 05/PU/1827746, 09/PU/1871197, 05/PU/1862015, 05/PU/1916699, 05/PU/1978484, 05/PU/1933340, 05/PU/2003625, 05/PU/2006023, 05/PU/1967240, 05/PU/1829538, 05/PU/1908373, 09/PU/1922732

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)