Skip to content
AltUrb
Granted

Rue Philippe Baucq 4

Etterbeek · 05/PU/1877402 · Permis d'urbanisme privé

Rue Philippe Baucq 4, Etterbeek: new construction. Case octroyé, lodged on 1 January 1913. The decision was notified on 4 September 1913, 246 days after lodging.

CONSTRUIRE une maison 850 m³ THIJS J, d
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 January 1913date the file was received
Decision notified4 September 1913246 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
42 mHeavy renovationrégulariser les travaux non-conformes au permis de 2008 en ce qui concerne la modification de la porte d'entrée (façade2025
42 mExtension or raisingrénover et modifier la volumétrie d'une maison unifamiliale (annexe, lucarnes, terrasse, panneaux solaires)2023
48 mMerger of dwellingsréunir deux appartements en un appartement de trois chambres et rénover l'ensemble2022
48 mExtension or raisingconstruire une extension au 2ème étage d'une maison unifamiliale afin d'agrandir une chambre2023
63 mOffice conversionmodifier le permis d'urbanisme 10686 en ce qui concerne le changement d'affectation d'un équipement (cabinet médical) en2022

Other nearby cases : 05/PU/1857006, 05/PU/1866990, 05/PU/2041004, 05/PU/2040873, 05/PU/1945178, 05/PU/1997290, 05/PU/1891760, 05/PU/1902653, 05/PU/2035787, 05/PU/2014521, 05/PU/2041127, 05/PU/1971899, 05/PU/1839034, 05/PU/1894507, 05/PU/1869687, 05/PU/2003322, 05/PFD/1846857, 05/PFD/2037718, 05/PU/1858060, 05/PU/1894252, 05/PU/1897754, 05/PU/2038942, 05/PU/2001174, 05/PU/1969845, 05/PU/1865994

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)