Rue des Aduatiques 59
Etterbeek · 05/PU/1877886 · Permis d'urbanisme privé
Rue des Aduatiques 59, Etterbeek: new construction. Case octroyé, lodged on 1 January 1933. The decision was notified on 23 October 1933, 295 days after lodging.
CONSTRUIRE une maison à 3 étages 1231 m³ DUCROT-DESIRANT Vve, d| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 January 1933 | date the file was received |
| Decision notified | 23 October 1933 | 295 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 57 m | Roof | régulariser, en application de l'article 330§3 du CoBAT, l'aménagement d'une terrasse sur une toiture plate au rez arriè | 2024 |
| 58 m | Split into dwellings | régulariser la construction d'une toiture à versant, l’aménagement d’un logement au 3e étage d'un immeuble comportant de | 2026 |
| 64 m | Façade and windows | isoler les deux pignons mitoyens et régulariser l'isolation de la façade arrière | 2022 |
| 69 m | Façade and windows | isoler le pignon droit d'une maison unifamiliale | 2023 |
| 70 m | Tree felling | abattre un arbre (sorbier) en zone de cours et jardin | 2023 |
Other nearby cases : 05/AA/1991425, 05/PU/1905205, 05/PU/1938563, 05/PU/2040466, 05/PU/1957041, 05/PU/2036115, 05/PU/1849160, 05/PU/1978200, 05/PU/1823803, 05/PU/1837238, 05/PU/1820549, 05/PU/2011294, 05/PU/1974320, 05/PU/1848595, 05/PU/1844090, 05/PFU/1962116, 05/PU/1940054, 05/PU/1895023, 05/PU/1983283, 05/PU/2036386, 05/PFD/1957774, 05/GOU_PU/1941568, 05/PU/1901761, 05/PFU/2002067, 05/PU/2017026
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)