Avenue Eudore Pirmez 39
Etterbeek · 05/PU/1878547 · Permis d'urbanisme privé
Avenue Eudore Pirmez 39, Etterbeek: new construction. Case octroyé, lodged on 1 January 1923. The decision was notified on 27 September 1923, 269 days after lodging.
CONSTRUIRE une maison de 6 m de façade 872 m3 IDIERS F, d| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 January 1923 | date the file was received |
| Decision notified | 27 September 1923 | 269 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 11 m | Roof | construire en toiture une terrasse et un volume d’accès, liés au logement 3 chambres, installer des panneaux solaires et | 2023 |
| 30 m | Heavy renovation | Rénover 2 immeubles de logements sociaux, aménager leurs combles ainsi que leurs jardins | 2022 |
| 39 m | Split into dwellings | régulariser la division d'une maison unifamiliale, réduire le nombre d'unité à 2 appartements 1 chambre et 1 duplex 3 ch | 2023 |
| 53 m | Extension or raising | régulariser la modification de la volumétrie en intérieur d’îlot, la démolition d'un atelier et le réaménagement de 42 e | 2026 |
| 65 m | Façade and windows | Isoler la façade arrière d'une maison unifamiliale | 2025 |
Other nearby cases : 05/PU/1864947, 05/PU/1982631, 05/PU/1962472, 05/PU/1862491, 05/PFD/2038337, 05/PU/1991717, 05/PU/1945318, 05/PU/1901730, 05/PU/1955009, 05/PU/1866073, 05/PU/1865994, 05/PU/1969845, 05/PU/2001174, 05/PU/1959164, 05/PU/1903190, 05/PU/1853977, 05/PU/1986247, 05/PU/2017485, 05/PU/1858060, 05/PU/1945178, 05/PU/1869474, 05/PU/1894507, 05/PU/1975336, 05/PU/1855175, 05/PU/1931163
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)