Skip to content
Altaica Urban
Granted

Chaussée de Wavre 655

Etterbeek · 05/PU/1879267 · Permis d'urbanisme privé

Chaussée de Wavre 655, Etterbeek: new construction. Case octroyé, lodged on 1 January 1910. The decision was notified on 25 November 1910, 328 days after lodging.

CONSTRUIRE une maison n° 655 GINOT Emile, d
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 January 1910date the file was received
Decision notified25 November 1910328 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
15 mExtension or raisingagrandir et rénover afin de passer de 3 à 4 logements dans un immeuble avec commerce au demi-sous-sol2022
15 mEnergy worksRégulariser la situation existante du bâtiment; placer un nouveau groupe de traitement d'air dans la salle Chaplin2026
15 mSplit into dwellingsmodifier la volumétrie (façade arrière et toiture) et le nombre de logements (passage de 3 à 4) ainsi que réaménager l'e2024
34 mRetail or horeca fit-outrégulariser les modifications apportées à la vitrine d'un commerce ainsi que le placement d'une enseigne2024
35 mMerger of dwellingsréunir deux commerces aux rez de deux immeubles mixtes2023

Other nearby cases : 05/PU/1991717, 05/PU/1939231, 05/PU/1906995, 05/PU/1853977, 05/PU/1931163, 05/PU/1945318, 05/PU/1862491, 05/PU/2021463, 05/PU/1962472, 05/PU/2012923, 05/PU/2004279, 05/PU/2017485, 05/GOU_PU/2042339, 05/PU/1986247, 05/PU/2033309, 05/PU/1867247, 05/PU/1833421, 05/PU/1977759, 05/PU/1959352, 05/PU/1910249, 05/PU/1836711, 05/GOU_PU/1926553, 05/PU/1959164, 05/PU/1865994, 05/PU/1966368

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)