Avenue Edmond Mesens 63

Etterbeek · 05/PU/1886108 · Permis d'urbanisme privé

Avenue Edmond Mesens 63, Etterbeek: new construction. Case octroyé, lodged on 1 January 1928. The decision was notified on 7 June 1928, 158 days after lodging.

CONSTRUIRE une maison de 7 m de façade 1214 m³ GUERSON, d
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 January 1928date the file was received
Decision notified7 June 1928158 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
9 mFaçade and windowsrégulariser, en application de l'article 330§3 du CoBAT, la modification des menuiseries en façade (hors porte de garage2025
33 mHeavy renovationrégulariser les modifications apportées à une maison individuelle (volumétrie, aspect des façades avant et arrière), ouv2025
43 mFaçade and windowsremplacer les châssis au premier étage en façade à rue côté gauche2022
47 mDemolitionrégulariser la démolition d'une corniche décorative2024
55 mExtension or raisingconstruire une annexe sur deux niveaux (sous-sol et rez-de-chaussée) en façade arrière, aménager une terrasse sur la toi2024

Other nearby cases : 05/PU/2016827, 05/PU/1952530, 05/PU/2011013, 05/PU/1850090, 19/PU/1923884, 05/AA/1826770, 05/PU/1976199, 19/PU/1894178, 19/PU/1958072, 19/PU/1978694, 05/PU/1941645, 19/PU/1981425, 19/SFD/1839608, 19/PU/1835317, 19/PU/1963690, 19/PU/1854579, 19/PU/1939112, 05/AA/1832838, 05/PFD/2012807, 19/SFD/1828077, 05/PU/1833077, 05/PU/1810237, 05/PU/1925984, 19/AA/1842827, 19/PU/1915445

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)