Avenue du Front 24
Etterbeek · 05/PU/1886651 · Permis d'urbanisme privé
Avenue du Front 24, Etterbeek: new construction. Case octroyé, lodged on 1 January 1936. The decision was notified on 23 March 1936, 82 days after lodging.
CONSTRUIRE une maison à deux étages 960 m³ VAN CAUWELAERT Henri, d| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 January 1936 | date the file was received |
| Decision notified | 23 March 1936 | 82 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 42 m | Public space | - Elargissement de la berme centrale transformée en noue. - Remplacer l'asphalte du côté pair de l'avenue. - Pose d'un b | 2026 |
| 58 m | Extension or raising | régulariser la construction d'une terrasse au rez (centre à droite) et en intégrer une partie au volume construit en faç | 2024 |
| 64 m | Tree felling | abattre un arbre | 2021 |
| 73 m | Split into dwellings | régulariser la division d'un appartement au 4ème étage en deux appartements 2 chambres | 2022 |
| 85 m | Other | Installer de nouveaux équipements de télécommunication mobile pour Telenet sur la façade du clocher d’une église existan | 2025 |
Other nearby cases : 05/PFD/2026533, 05/PU/1907207, 05/PU/1943213, 05/PU/1896346, 05/PU/1810274, 05/PU/2002468, 05/CU/1958873, 05/PU/1961760, 05/PU/1946808, 05/PU/1968021, 05/PU/1915374, 05/PU/1863581, 05/PU/1854446, 05/PU/1852648, 05/PU/1995441, 05/PFD/1939220, 05/PU/1942712, 05/PU/1825384, 05/PU/1866743, 05/PU/1847315, 05/PU/1837850, 05/PU/2004927, 05/PU/2010082, 05/PU/2034674, 05/PU/1860620
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)