Rue Baron de Castro 14

Etterbeek · 05/PU/1887751 · Permis d'urbanisme privé

Rue Baron de Castro 14, Etterbeek: new construction. Case octroyé, lodged on 1 January 1929. The decision was notified on 8 May 1929, 127 days after lodging.

CONSTRUIRE une maison 1118 m³ BAILLEUL, d
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 January 1929date the file was received
Decision notified8 May 1929127 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
7 mTree fellingabattre un arbre (Thuya) en zone de cours et jardin2023
10 mRoofrégulariser les travaux non-conformes au permis d'urbanisme 9646 dont la construction d'une lucarne rentrante avec terra2022
35 mExtension or raisingconstruire une annexe, réaménager une maison unifamiliale, créer des nouvelles baies en façade arrière, isoler la façade2023
35 mExtension or raisingrégulariser, en application de l'article 330§3 du CoBAT, les modifications apportées à une maison unifamiliale : façade 2022
44 mTree fellingabattre 4 cerisiers et replanter 4 arbres indigènes dans la cour intérieure et dans le jardin2026

Other nearby cases : 05/PU/2031142, 05/PU/1992923, 05/PU/1936284, 05/PU/1976000, 05/PU/1935883, 05/PU/2043380, 05/PU/1855170, 05/PU/1909330, 05/PU/1972223, 05/PU/1833077, 05/PU/1810237, 05/AA/1832838, 05/ECO/1932611, 05/PU/1941645, 05/PU/1925984, 05/PU/1892023, 05/PU/1976199, 05/PU/1935034, 05/PU/1896249, 05/PU/1844377, 05/PU/1903217, 05/PU/1914198, 05/PU/2030383, 05/PU/1842771, 05/PFD/1895513