Boulevard Saint-Michel 27

Etterbeek · 05/PU/1888537 · Permis d'urbanisme privé

Boulevard Saint-Michel 27, Etterbeek: new construction. Case octroyé, lodged on 1 January 1918. The decision was notified on 13 August 1918, 224 days after lodging.

CONSTRUIRE un hôtel de 11 m de façade 4149 m³ BRICHARD, d
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 January 1918date the file was received
Decision notified13 August 1918224 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
26 mFaçade and windowsremplacer la porte d'entrée de l'immeuble2022
26 mFaçade and windowsremplacer la porte de garage de l'immeuble2024
33 mChange of usechanger l'affectation d'un commerce (restaurant) en un logement une chambre avec garage au rez et sous-sol d'un immeuble2024
37 mHeavy renovationrénover un appartement de deux chambres dans un immeuble de logements2022
39 mRoofmodifier le permis d'urbanisme 10966 en ce qui concerne l'aménagement d'une terrasse en toiture, côté Boulevard, et la c2023

Other nearby cases : 05/PU/1953588, 19/PU/1947929, 05/PU/1955747, 19/PU/1947917, 05/PU/1957579, 19/PU/1850203, 05/PU/1928784, 05/PFD/2008237, 05/PU/1830468, 05/PU/1893423, 05/PU/1830383, 05/GOU_PU/2035671, 05/PU/1950330, 19/PU/1869854, 05/PU/2039503, 19/PU/1846263, 05/PU/1943942, 19/PU/1996926, 19/PU/1928892, 05/PU/1922249, 05/SFD/2040593, 05/PU/1977451, 05/PU/2001486, 05/PU/1967161, 05/PU/1893443

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)