Rue du Clocher 44, Etterbeek: extension or raising. Case octroyé, lodged on 1 January 1954. The decision was notified on 18 March 1954, 76 days after lodging.
Construire annexe et WC 50,495 m3 BOLAIN Alexis, d| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 January 1954 | date the file was received |
| Decision notified | 18 March 1954 | 76 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 32 m | Roof | modifier le revêtement de la toiture à versants ainsi que l'isoler par l'extérieur (sarking) | 2023 |
| 33 m | Energy works | installer une pompe à chaleur dans le jardin, le long de la façade arrière | 2024 |
| 48 m | Energy works | isoler l'annexe arrière d'une maison unifamiliale | 2025 |
| 48 m | Façade and windows | isoler le pignon gauche d'un immeuble de logements | 2025 |
| 51 m | Split into dwellings | régulariser l'aménagement d'un 5e logement (2 chambres) dans les combles d'un immeuble, la modification des châssis au 4 | 2025 |
Other nearby cases : 05/PU/1970223, 05/PU/1983852, 05/PU/1935543, 05/PU/2040819, 05/PU/1967563, 05/PU/2005885, 05/PU/1922615, 05/PU/1857533, 05/PU/2027570, 05/PU/2040598, 05/PU/2010415, 05/PU/1966173, 05/PU/2002132, 05/PU/1912274, 05/PU/1913863, 05/PU/1836918, 05/PU/1859438, 05/PU/1811262, 05/PU/1825782, 05/PU/1992723, 05/PU/1952180, 05/PU/1947273, 05/PU/1922927, 05/PU/1825167, 05/PU/1867225
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)