Rue des Champs 58, Etterbeek: new construction. Case octroyé, lodged on 1 January 1914. The decision was notified on 16 February 1914, 46 days after lodging.
CONSTRUIRE une maison 569 m3 GUIOT E, d| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 January 1914 | date the file was received |
| Decision notified | 16 February 1914 | 46 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Tree felling | abattre un arbre (prunus) en zone de cours et jardin | 2023 |
| 12 m | New construction | ériger une cabane préfabriquée de 20m² dans le jardin | 2024 |
| 26 m | Extension or raising | régulariser l'extension du logement du rez vers le sous-sol arrière, la pose d'un escalier intérieur de liaison et la mo | 2026 |
| 36 m | Retail or horeca fit-out | régulariser la modification de la vitrine d'un commerce et placer une extraction de hotte en intérieur d’Îlot (commerce | 2024 |
| 40 m | Façade and windows | Placer une porte d’entrée coulissante avec une porte de secours adjacente dans une ouverture de fenêtre existante, et in | 2025 |
Other nearby cases : 05/PFD/1935586, 05/PU/1835644, 05/PU/1989085, 05/SFD/1827326, 05/PU/1899921, 05/PU/1960594, 05/PU/1858229, 05/PU/1820075, 05/PU/1851091, 05/SFD/1825440, 05/PU/1928318, 05/PU/1952752, 05/PFD/1998730, 05/PU/1904771, 05/PU/2014783, 05/PU/2006796, 05/PU/1917073, 05/SFD/1825121, 05/PU/2003264, 05/PU/1974832, 05/PU/1928950, 05/PU/2031925, 05/PU/1962416, 05/PU/1946993, 05/PU/1936331
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)