Rue Général Leman 119, Etterbeek: new construction. Case octroyé, lodged on 31 December 1874. The decision was notified on 25 March 1875, 84 days after lodging.
Construire une maison avec salle de café au rez, à l'angle de la rue des Rentiers 119 et de l'av d'Auderghem 140 LUCIEN Jérôme, cabaretier, d| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 31 December 1874 | date the file was received |
| Decision notified | 25 March 1875 | 84 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Public space | régulariser les barrières fixes posées en voirie | 2023 |
| 13 m | Façade and windows | peindre la façade avant en gris ardoise | 2022 |
| 27 m | Change of use | changer d'affectation le bureau lié au commerce en appartement deux chambres au 1er étage de l'immeuble et y aménager un | 2025 |
| 53 m | Split into dwellings | diviser une maison unifamiliale avec commerce en un bureau au rez avant et deux logements, démolir une partie de l'annex | 2024 |
| 58 m | Façade and windows | modifier la vitrine d'un rez commercial | 2026 |
Other nearby cases : 05/PU/1833747, 05/PU/2005885, 05/PU/1999978, 05/PU/1970223, 05/PU/2040819, 05/PU/1967563, 05/PU/2002132, 05/PU/1836918, 05/PU/1941899, 05/PU/2027570, 05/PU/1968382, 05/PU/1922615, 05/PU/1979915, 05/PU/2035209, 05/PU/1971844, 05/PU/1904269, 05/PU/2010415, 05/PU/1914142, 05/PU/1811262, 05/PU/1935543, 05/PU/1828023, 05/PU/1827262, 05/SFD/1825423, 05/PU/1830403, 05/PU/1931208