Granted

Place du Quatre Août 5

Etterbeek · 05/PU/1890868 · Permis d'urbanisme privé

Place du Quatre Août 5, Etterbeek: new construction. Case octroyé, lodged on 1 January 1954. The decision was notified on 15 July 1954, 195 days after lodging.

CONSTRUIRE un immeuble à 4 étages 4877,322 m3 Place du Quatre Août n° 4 et rue de Pervyse n° 1 LOUTSCH Emile,d
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on1 January 1954date the file was received
Decision notified15 July 1954195 days
Floor areasnot reported by the source
Competent authorityEtterbeek

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
42 mRoofisoler la toiture, les pignons et la façade arrière de l'immeuble2024
45 mPublic space- Elargissement de la berme centrale transformée en noue. - Remplacer l'asphalte du côté pair de l'avenue. - Pose d'un b2026
64 mTree fellingabattre un arbre2021
66 mExtension or raisingrégulariser l'extension de l'appartement du 2ème vers les combles, les modifications apportées à l'immeuble à ces niveau2023
78 mExtension or raisingconstruire une annexe au rez, deux lucarnes et une terrasse en toiture ainsi qu’isoler les pignons d'un immeuble de 4 lo2024

Other nearby cases : 05/PU/1810274, 05/PU/1837850, 05/PU/2004927, 05/PFD/2004511, 05/PFD/2026533, 05/PU/1942269, 05/PU/1854446, 05/PU/1896346, 05/PU/1852648, 05/PU/1860620, 05/PU/2034674, 05/PU/1825384, 05/PU/1957766, 05/PU/1863581, 05/PU/1915374, 05/PU/1847315, 05/PU/1866743, 05/PU/1905905, 05/PU/2035936, 05/PU/1834585, 05/PU/2009824, 05/PU/2035592, 05/PU/1843163, 05/PU/2002468, 05/CU/1958873