Rue des Boers 95
Etterbeek · 05/PU/1891622 · Permis d'urbanisme privé
Rue des Boers 95, Etterbeek: new construction. Case octroyé, lodged on 1 January 1912. The decision was notified on 23 August 1912, 235 days after lodging.
CONSTRUCTION une maison avec atelier 955 m³ & 305 m³ COULLAIS, d| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 January 1912 | date the file was received |
| Decision notified | 23 August 1912 | 235 days |
| Floor areas | — | not reported by the source |
| Competent authority | Etterbeek |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 23 m | Heavy renovation | transformer et rénover une habitation, et régulariser des éléments existants | 2026 |
| 25 m | Split into dwellings | régulariser la division du logement d'un immeuble mixte (commerce, atelier et 1 logement) en 3 appartements ainsi que l' | 2024 |
| 43 m | Change of use | régulariser la division d'une maison unifamiliale en 3 logements, la transformation d'un bâtiment arrière (atelier) en u | 2024 |
| 43 m | Split into dwellings | régulariser la division d'une maison unifamiliale en 3 logements et la transformation d'un bâtiment arrière (atelier) en | 2026 |
| 47 m | Extension or raising | régulariser la fermeture du balcon arrière et les aménagements intérieurs du logement du 3ème étage | 2022 |
Other nearby cases : 05/PU/1910502, 05/PU/2041340, 05/PU/1951491, 05/PU/1918469, 05/PU/2024360, 05/PU/1904071, 05/PU/1964600, 05/PU/1980251, 05/PU/1967399, 05/PU/1934509, 05/PU/1968161, 05/PU/2012502, 05/PU/2031625, 05/AA/1900093, 05/PU/1866697, 05/PU/2024857, 05/PU/2037711, 05/PU/1868321, 05/PU/2037228, 05/PU/1943120, 05/PU/2040713, 05/PU/2000521, 05/PU/1966000, 05/PU/2012218, 05/PU/1972964
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)