Granted
Avenue de Schiphol 2–6
Evere · 06/IPE/1781352 · Permis d'environnement
Avenue de Schiphol 2–6, Evere: operation of installations. Case octroyé, lodged on 18 March 2021. The decision was notified on 6 July 2022, 475 days after lodging.
Exploitation| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 March 2021 | date the file was received |
| Public inquiry | 16 August 2021 – 15 September 2021 | |
| Consultation committee | 23 September 2021 | |
| Decision notified | 6 July 2022 | 475 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 157 m | Change of use | Changer l'affectation d'un bureau et d'un espace de stockage avec parking extérieur en école primaire avec cour de récré | 2025 |
| 170 m | Extension or raising | étendre une maison unifamiliale et abattre 1 arbre (souche à trois troncs) | 2023 |
| 170 m | Split into dwellings | diviser une maison mitoyenne unifamiliale en deux logements distincts | 2025 |
| 174 m | Change of use | functiewijziging van de gelijkvloerse verdieping en wijziging inrichting achterliggende parking | 2026 |
| 182 m | New construction | Projet initial: Transformer un immeuble d'hôtel en un immeuble de 83 logements et création d'un commerce et un espace de | 2022 |
Other nearby cases : 06/PU/1833406, 06/PU/2039078, 06/PFD/1927683, 06/PU/2005469, 06/PU/2005479, 06/PFD/1866598
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)