Granted
Avenue de l'Andalousie 9
Evere · 06/IPEPLP/560735 · Prolongation de PE
Avenue de l'Andalousie 9, Evere: operation of installations. Case octroyé, lodged on 18 March 2015. The decision was notified on 28 July 2015, 132 days after lodging.
Immeuble de logements| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 18 March 2015 | date the file was received |
| Decision notified | 28 July 2015 | 132 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 57 m | Tree felling | abattre un arbre à haute tige sur un espace public | 2021 |
| 57 m | Extension or raising | het bouwen van een veranda / construire une véranda _ SANS SUITE | 2024 |
| 74 m | Façade and windows | Mettre en conformité la porte d'entrée | 2022 |
| 88 m | Extension or raising | étendre un appartement situé au dernier étage de l'immeuble | 2025 |
| 109 m | Tree felling | abattre un arbre à haute tige | 2022 |
Other nearby cases : 06/PU/2035151, 06/PFD/1845362, 06/PU/2011822, 06/PU/1849035, 06/PFD/1849153, 06/PFD/1994713, 06/PU/2035620, 06/PU/2031927, 06/PFD/1866384, 06/PU/1827973, 06/SFD/1823032, 06/PU/1851495, 06/SFD/1866127, 06/PU/1936629, 06/PU/2040136, 06/PU/1859520, 06/PU/1855832, 06/PU/1892658, 06/PU/1994810
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)