Skip to content
Altaica Urban
Granted

Avenue des Communautés 5

Evere · 06/PFD/655229 · Permis d'urbanisme délivré par le FD

Avenue des Communautés 5, Evere: demolition and reconstruction. Case octroyé, lodged on 26 October 2017. The decision was notified on 5 March 2019, 495 days after lodging. It removes 4 296 m² of office space.

Démolir le site existant composé d' immeubles de bureaux et d' entrepôts afin de construire un retailparc (composé de 2 bâtiments avec 6 unités de commerce de minimum 500 m² ) comportant un parking en plein air pour 123 voitures .
The application's own description, in its source language (FR). Source: Nova.
4 296
Office floor area removed
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on26 October 2017date the file was received
Public inquiry21 March 2018 – 5 April 2018
Consultation committee19 April 2018
Decision notified5 March 2019495 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
6 mSigns and advertisingplaatsen van uithangborden (Brico)2021
6 mSigns and advertisingplaatsen van uithangborden (Electro Depot)2021
69 mExtension or raisingEtendre le bâtiment de selfstorage et modifier la façade avant2024
105 mSigns and advertisingmaintenir un panneau publicitaire éclairé de 8 m².2021
105 mSigns and advertisingremplacer un panneau publicitaire de 8m² déroulant par un panneau non déroulant de 16m²2025

Other nearby cases : 06/PFD/2016637, 06/PFD/1844347, 06/GOU_PU/1841497, 06/PU/1825361, 06/PU/1847645, 18/PU/1969312, 06/PFD/1859670, 06/GOU_PU/1958599, 06/PU/1852870

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)