Rue Pierre Van Obberghen 19
Evere · 06/PU/1713238 · Permis d'urbanisme privé
Rue Pierre Van Obberghen 19, Evere: heavy renovation. Case refusé, lodged on 17 May 2019. The decision was notified on 23 September 2021, 860 days after lodging. The project creates 17 m² of housing.
mettre en conformité les transformations de l'immeuble.| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Refusé | |
| Lodged on | 17 May 2019 | date the file was received |
| Decision notified | 23 September 2021 | 860 days |
| Competent authority | Evere |
Timeline
- Application lodged
- Decision notified · Refused
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 6 m | Extension or raising | Mettre en conformité les modifications apportées à l'immeuble (nombre et répartition des logements, extension en façade | 2022 |
| 6 m | Energy works | installer une unité de pompe à chaleur au 2ème étage, en façade arrière d'un immeuble de logements | 2026 |
| 6 m | Extension or raising | Mettre en conformité les modifications apportées à l'immeuble (nombre et répartition des logements, extension en façade | 2023 |
| 33 m | Extension or raising | het uitbreiden van het gelijkvloers en het wijzigen van het woningaantal | 2023 |
| 37 m | Extension or raising | rénover et étendre une maison unifamiliale. | 2025 |
Other nearby cases : 06/PU/1918658, 06/PU/1995279, 06/PU/1821055, 06/PU/1828850, 06/PU/1938755, 06/PU/1846237, 06/PFD/1829452, 06/PU/2044933, 06/SFD/1824681, 06/PU/1965426, 06/PU/1925270, 06/PU/1987712, 06/PU/1995824, 06/PU/1963556, 06/PU/2002947, 06/PU/1865190, 06/SFD/1965402, 06/PU/1933337, 06/PU/1938545, 06/PU/1937622, 06/PU/1905425, 06/GOU_PU/1941451, 06/GOU_PU/1936666, 06/PU/1843384, 06/PU/1856624
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)