Granted
Avenue de l'Optimisme 91–95
Evere · 06/PU/1726153 · Permis d'urbanisme privé
Avenue de l'Optimisme 91–95, Evere: new construction. Case octroyé, lodged on 20 September 2019. The decision was notified on 18 January 2021, 486 days after lodging.
installer une cabine de gaz (SIBELGA) en zone de cours et jardins.| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 September 2019 | date the file was received |
| Public inquiry | 31 August 2020 – 15 September 2020 | |
| Consultation committee | 24 September 2020 | |
| Decision notified | 18 January 2021 | 486 days |
| Floor areas | — | not reported by the source |
| Competent authority | Evere |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 36 m | Façade and windows | modifier partiellement la façade d'un immeuble (changement de châssis) | 2024 |
| 69 m | Façade and windows | modifier l'aspect des façades. | 2021 |
| 116 m | Change of use | modifier l'utilisation d'une activité productive (en une autre activité productive) et mettre en conformité la fermeture | 2022 |
| 116 m | Change of use | modifier l'utilisation d'un activité productive (en une autre activité productive) et mettre en conformité la fermeture | 2022 |
| 126 m | Office conversion | mettre en conformité le changement de destination d'un bureau en logement au rez-de-chausséé gauche | 2026 |
Other nearby cases : 06/PU/1871474, 06/PU/1832753, 06/SFD/1964379, 06/PU/1947088, 06/PU/1844353, 06/PU/1967498, 06/SFD/1983248, 06/PU/1956915, 06/PU/1856513, 06/PP/2023715, 06/PFD/2029850, 06/PU/1980533, 06/PU/2018689, 06/PU/1995631, 06/PFD/2001406
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)