Avenue Franz Guillaume 56
Evere · 06/PU/1852483 · Permis d'urbanisme privé
Avenue Franz Guillaume 56, Evere: split into dwellings. Case octroyé, lodged on 11 August 2022. The decision was notified on 14 March 2023, 215 days after lodging. The project creates 74 m² of housing.
mettre en conformité le nombre de logement| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 August 2022 | date the file was received |
| Decision notified | 14 March 2023 | 215 days |
| Competent authority | Evere |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 30 m | Public space | Remplacer l'éclairage public par de nouvelles armatures et LED dans toute la rue. | 2025 |
| 58 m | Façade and windows | installer un garde corps/grille devant les fenêtres du rez-de-chaussée | 2024 |
| 60 m | Merger of dwellings | mettre en conformité la réunification de 2 appartements en 1 seule unité de logement ainsi que son extension, au 6ème ét | 2024 |
| 65 m | Heavy renovation | Modifier le permis d'urbanisme référencé 06/PFD/1775237 et délivré le 23/12/2021, en réaménageant le sous-sol d'un immeu | 2024 |
| 75 m | Façade and windows | modifier l'aspect des façades du dernier étage (penthouse) et installer pour vélos au sous-sol. | 2024 |
Other nearby cases : 06/PU/1859729, 06/PU/2005909, 06/PU/1943537, 06/SFD/1897457, 06/PU/1844679, 06/PU/1979908, 06/PU/2040477, 06/PFD/1865001, 06/PU/2037039, 06/PU/2020340, 06/PU/1930679, 06/PU/1810582, 06/GOU_PL/1970341, 06/LPFD/1845224, 06/PU/1849514, 06/GOU_PU/1831877, 06/SFD/1917624, 06/PU/1823162, 06/PU/1800295, 06/PU/1902094, 06/SFD/1917866, 06/PU/1925235, 06/PU/1942517, 06/SFD/1822749, 06/PU/2027135
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)