Rue Jean-Baptiste Bauwens 21
Evere · 06/PU/2012690 · Permis d'urbanisme privé
Rue Jean-Baptiste Bauwens 21, Evere: façade and windows. Case octroyé, lodged on 8 December 2025. The decision was notified on 7 May 2026, 150 days after lodging.
isoleren van de gevels en het schrijnwerk vervangen| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 8 December 2025 | date the file was received |
| Public inquiry | 2 February 2026 – 17 February 2026 | |
| Consultation committee | 26 February 2026 | |
| Decision notified | 7 May 2026 | 150 days |
| Floor areas | — | not reported by the source |
| Competent authority | Evere |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 13 m | Tree felling | installer un escalier en zone de cours et jardins. | 2023 |
| 44 m | Extension or raising | mettre en conformité la zone de recul et la façade avant, étendre et diviser une maison unifamiliale en plusieurs logeme | 2025 |
| 66 m | Heavy renovation | Modifier le rez-de-chaussée (permis modificatif du permis n° 2021-163-10) | 2024 |
| 67 m | — | 06/PU/2024378 | 2026 |
| 68 m | Roof | rénover les terrasses et remplacer les garde-corps de la section n°8 de l'immeuble Oud-Kapelleke | 2025 |
Other nearby cases : 06/PU/2026168, 06/PFD/2026332, 06/PU/2017708, 06/PU/1938705, 06/PU/1993774, 06/PU/2037129, 06/PU/1979822, 06/PFD/2014974, 06/PU/1838222, 06/PU/1895699, 06/PU/1954882, 06/PU/1842979, 06/PU/1929619, 06/PFD/1830240, 06/PU/1929710, 06/PU/2041848, 06/PU/1976876, 06/PU/1866252, 06/PU/1975033, 06/PU/1831795, 06/PU/2024243, 06/SFD/1833562, 06/PU/1896517, 06/PU/1951032, 06/PU/1914661
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)