Skip to content
AltUrb
Granted

Chemin d'Accès 36

Forest · 07/GOU_PU/1858035 · Permis d'urbanisme – recours au Gouvernement

Chemin d'Accès 36, Forest: change of use. Case octroyé, lodged on 28 September 2022. The decision was notified on 12 May 2023, 226 days after lodging.

Changer la destination d'un ensemble d'immeuble de commerce en bureau et mettre en conformité la modification des châssis
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme – recours au Gouvernement
StatusOctroyé
Lodged on28 September 2022date the file was received
Decision notified12 May 2023226 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mChange of useChanger la destination d'un ensemble d'immeuble de commerce en bureau et mettre en conformité la modification des châssi2022
0 mPublic spaceRénover les auvents originaux de la gare de Forest-Est2022
59 mPublic spaceRenouveler le tablier et les garde-corps du pont de la gare de Forest-Est2023
61 mSplit into dwellingsModifier le nombre et la répartition des logements de 1 à 3 avec aménagement des combles, réaliser des annexes et terras2022
61 mFaçade and windowsModifier la façade à rue (vitrine et portes d'entrée)2025

Other nearby cases : 07/PU/2025130, 07/PU/1964780, 07/PFD/2032397, 07/PU/2039273, 07/PU/2038528, 07/PU/2019095, 07/PFD/2017774, 07/PU/1943530, 07/GOU_PU/1853912, 07/SFD/1851196, 07/PU/1824674, 07/PU/1852953, 07/PU/1909788, 07/PU/1860128, 07/PU/1847560, 07/PU/1892445, 07/SFD/1915526, 07/PU/1939102, 07/SFD/1962388, 07/PU/1943413, 07/PU/1828430, 07/PFD/1966601, 07/PU/1985413, 07/PU/1912703, 07/SFD/1945884

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)