Skip to content
Altaica Urban
Refused

Chaussée de Neerstalle 91–105

Forest · 07/IPE/527228 · Permis d'environnement

Chaussée de Neerstalle 91–105, Forest: operation of installations. Case refusé, lodged on 12 May 2014. The decision was notified on 22 December 2014, 224 days after lodging.

Demande d’exploitation d’un ensemble de 5 bâtiments à construire comprenant 1 maison de repos, 1 résidence-service et 3 immeubles de logements.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusRefusé
Lodged on12 May 2014date the file was received
Decision notified22 December 2014224 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Refused

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mHeavy renovationMettre en conformité la modification de deux immeubles à appartements2022
0 mRegularisationMettre en conformité la modification de deux immeubles à appartements2022
40 mOtherMettre en conformité la modification du nombre de boxes de garage de 21 à 222025
55 mFaçade and windowsModifier les châssis du rez-de-chaussée2024
55 mFaçade and windowsModifier les châssis du rez-de-chaussée2024

Other nearby cases : 07/PU/1952348, 07/PU/1908678, 07/PU/1900252, 07/SFD/1849700, 07/SFD/1842063, 07/PU/1826268, 07/PU/1944149, 07/PU/1940103, 07/SFD/1963326, 07/PU/1940481, 07/PU/1824571, 07/PU/2005424, 07/PU/1911352, 07/PU/1955901, 07/PU/1900544, 07/PU/2032627, 07/PU/1950604, 07/PU/1905657, 07/PU/1850143, 07/PU/1859604, 07/PU/1909243, 07/PU/1838295, 07/PU/1951325, 07/PU/1967233, 07/PU/1952622