Granted
Rue Lieutenant Lotin 40
Forest · 07/IPE/554267 · Permis d'environnement
Rue Lieutenant Lotin 40, Forest: operation of installations. Case octroyé, lodged on 1 December 2014. The decision was notified on 1 July 2015, 212 days after lodging.
Exploitation d'un centre de logistique| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 1 December 2014 | date the file was received |
| Decision notified | 1 July 2015 | 212 days |
| Works started | 1 April 2016 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 34 m | Façade and windows | mettre en conformité les modifications de baies, de circulation extérieure, la modification du parking couvert passant d | 2024 |
| 51 m | Demolition and reconstruction | Démolir et reconstruire des bâtiments d'entrepôts logistiques, modifications des circulations, avec un parking couvert | 2022 |
| 202 m | Other | Réaménager des emplacements de parking extérieur | 2022 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)