Skip to content
AltUrb
Withdrawn

Rue du Charroi 20

Forest · 07/IPEEXT/499206 · Extension / Transformation de PE

Rue du Charroi 20, Forest: new construction. Case annulé, lodged on 13 March 2014. The decision was notified on 17 April 2014, 35 days after lodging.

Extension de l’atelier TGV : extension du magasin général par la construction d’un nouveau bâtiment pour accueillir un dépôt plus grand de pièces métalliques.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeExtension / Transformation de PE
StatusAnnulé
Lodged on13 March 2014date the file was received
Decision notified17 April 201435 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.