Skip to content
AltUrb
Withdrawn

Rue du Charroi 21–23

Forest · 07/IPEPLP/443769 · Prolongation de PE

Rue du Charroi 21–23, Forest: operation of installations. Case annulé, lodged on 22 March 2004. The decision was notified on 13 August 2004, 144 days after lodging.

exploitation d'un poste de transformation 150/36/11 kV (1 seule prolongation pour 2 permis existants : PE 94/0228 et PE 96/0343)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusAnnulé
Lodged on22 March 2004date the file was received
Decision notified13 August 2004144 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.