Withdrawn
Rue du Charroi 21–23
Forest · 07/IPEPLP/443769 · Prolongation de PE
Rue du Charroi 21–23, Forest: operation of installations. Case annulé, lodged on 22 March 2004. The decision was notified on 13 August 2004, 144 days after lodging.
exploitation d'un poste de transformation 150/36/11 kV (1 seule prolongation pour 2 permis existants : PE 94/0228 et PE 96/0343)| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 22 March 2004 | date the file was received |
| Decision notified | 13 August 2004 | 144 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)